Gates: Two 20' gates in front, opening to a 40' entrance off street, one 12' gate in rear at exit from property. Both with remote openers, key pads, and an electric eye to prevent gate closing on vehicle entering or leaving: $22,354.50
Sealing and striping the parking lot:
Seal asphalt and stripe off car and truck parking, install handicap signs, stripe driveway all the way through property: $6,500.00
30' x 28' Addition on building, turnkey:
The addition will be the warehouse, shipping and receiving area for the ministry, and can house additional offices in the future if needed $35,000.00
Concrete Posts with Chains:
50 posts, 24” round 3’ high with 3' in ground @ $ 375.00 each: $18,750.00
Flag Pole:
Flag -- 8’ x 12’ & 45 ft. Pole installed: $1,200.00 (UPDATE-Paid and installed)
LED Cross:
Single-face Cross, 14’ x 9’ 7’’, red LED, installed, 45’ to top: $2,200.00 (UPDATE- 8/20/2010 This item has been paid for by Bob and Susan Ryan! PTL!!)
Sign for Building:
One single-face sign for building as per approved sketch, 2’ x 17’6’’: $1,300.00
Total Project = $ 87,304 .50. Total Still Needed = $65,158.50.